"On 20 January 2011, Mirvac stated it will not charge any margin or for its time in relation to the rectification works. Its estimate includes prospective costs of up to $1,000,000 for priority works (completion of clean up works currently underway, preliminary electrical works to enable restoration of power and preliminary fire control equipment), and costs of $2,950,000 (including priority works) to complete clean up works, to rectify damage to ground floor lobbies, lifts and the completion of works including electrical, fire and hydraulic works."