Monday, October 22, 2012

M&A Update

The M&A (McLachlan & Ann) mixed use development is under construction on Ann Street in the Valley.  The commercial tower has topped out, and is currently being fitted out for commercial tenants, with a move-in date expected in March 2013.  The residential tower is up to level 8 out of 21 levels, and is reported to be on schedule for completion in late 2013.  From the photo below, it can be seen that the towers are in a commercial area of the Valley, so it will be interesting to see how a residential development changes the character of this area.  It also appears that the residential adjoins the commercial tower in an L-shaped configuration, which blocks some of the aspect from some of the apartments.


No comments: